Hours of construction will be from 7 am to 5 pm. However, for roads receiving a slurry seal, road closures could extend beyond 5 pm. Please stay off all slurry sealed roads until the contractor removes the barricades after the slurry seal as sufficiently dried.
Friday, April 8th:
Electronic message board installation at entrance to LCPOA (Clinton Keith side)
Monday, April 11th:
Application of a herbicide to cracks in asphalt pavement in project area.
Thursday, April 14th:
Flagmen will be provided. Expect Delays
Work includes: Asphalt patching and repairs on:
- Avenida La Cresta (Avenida Bonita to Calle Centro)
- Avenida La Cresta (Avenida Castilla to Valle Vista)
Friday, April 15th:
Flagmen will be provided. Expect Delays
Work includes: Asphalt patching and repairs on:
- Paseo de Flores
- Valle Vista
- Via Majorca (Corte Del Riatillo to Dawn Ct.)
- Via Majorca (Paseo Montana to Via Vista Grande)
- Via Baya
Monday, April 18th:
Flagmen will be provided. EXpect Delays
Work includes: Asphalt crack filling activities:
- Via Majorca, South side (Paseo Montana to Via Vista Grande)
- Avenida La Cresta, North side (Avenida Bonita to Calle Centro)
Tuesday, April 19th:
Flagmen will be provided. Expect Delays
Work includes: Asphalt crack filling activities:
- Via Majorca, North Side (Paseo Montana to Via Vista Grande)
- Avenida La Cresta, South side (Avenida Bonita to Calle Centro)
Wednesday, April 20th:
Flagmen will be provided. Expect Delays
Work includes: Asphalt crack filling activities:
- Avenida La Cresta, South side (Avenida Castilla to Valle Vista)
Thursday, April 21st:
Flagmen will be provided. Expect Delays
Work includes: Asphalt crack filling activities:
- Avenida La Cresta, North side (Avenida Castilla to Valle Vista)
Friday, April 22nd:
Flagmen will be provided. Expect Delays
Work includes: Asphalt crack filling activities:
- Paseo De Flores
- Valle Vista (Avenida La Cresta to 1160’ South of Via Sevilla)
Monday, April 25th:
Flagmen will be provided. Expect Delays
Work includes: Asphalt crack filling activities:
- Via Majorca (Corte Del Riatillo to Dawn Ct.)
- Via Baya
Tuesday, April 26th:
Single Lane traffic. Flagmen will be provided. Expect Delays. Lane closed to 5 pm.
Work includes: Slurry seal application on:
- Avenida La Cresta, North side (Avenida Bonita to Calle Centro)
- Via Majorca, South Side (Paseo Montana to Via Vista Grande)
Wednesday, April 27th:
Single Lane traffic. Flagmen will be provided. Expect Delays. Lane closed to 5 pm.
Work includes: Slurry seal application on:
- Avenida La Cresta, South side (Avenida Bonita to Calle Centro)
- Via Majorca, North Side (Paseo Montana to Via Vista Grande)
Thursday, April 28th:
Single Lane traffic. Flagmen will be provided. Expect Delays. Lane closed to 5 pm.
Work includes: Slurry seal application on:
- Avenida La Cresta, South side (Avenida Castilla to Valle Vista)
Friday, April 29th:
Single Lane traffic. Flagmen will be provided. Expect Delays. Lane closed to 5 pm.
Work includes: Slurry seal application on:
- Avenida La Cresta, North side (Avenida Castilla to Valle Vista)
Monday, May 2nd:
NO WORK. Trash Pick Up Day.
Tuesday, May 3rd:
road closed on Valle Vista from 7 AM to 5 PM.
Work includes: Slurry seal application on:
- Valle Vista (Avenida La Cresta to 1160’ South of Via Sevilla). See Detour Map.
road closed on Paseo de flores from 7 AM to 5 PM.
Work includes: Slurry seal application on:
- Paseo De Flores (Avenida La Cresta to end of road).
Thursday, May 5th:
road closed on the following streets from 7 AM to 5 PM.
Work includes: Slurry seal application on:
- Via Majorca (Corte Del Riatillo to Dawn Ct.). See Detour Map.
- Via Baya (Via Majorca to end of road).
Monday, May 9th:
No road closures. please Slow down for workers.
Work includes: Striping work (1st coat) on the following streets:
- Avenida La Cresta (Avenida Bonita to Calle Centro)
- Avenida La Cresta (Avenida Castilla to Valle Vista))
- Paseo de Flores (Avenida La Cresta to end of road)
- Valle Vista (Avenida La Cresta to 1160’ South of Via Sevilla)
- Via Majorca (Paseo Montana to Via Vista Grande)
- Via Majorca (Corte Del Riatillo to Dawn Ct.)
- Via Baya (Via Majorca to end of road)
Monday, May 16th:
No road closures. please Slow down for workers.
Work includes: Striping (2nd coat) and pavement markers on the following streets:
- Avenida La Cresta (Avenida Bonita to Calle Centro)
- Avenida La Cresta (Avenida Castilla to Valle Vista))
- Paseo de Flores (Avenida La Cresta to end of road)
- Valle Vista (Avenida La Cresta to 1160’ South of Via Sevilla)
- Via Majorca (Paseo Montana to Via Vista Grande)
- Via Majorca (From Corte Del Riatillo to Dawn Ct.)
- Via Baya (Via Majorca to end of road)